92 Ltd contact information

Company Profile

Company History

Apart from Hydro Power development, Ninety Two Ltd has an experience in Hand loom Textile manufacturing business, Hotel and Entertainment management as well as Sports sector especially the Tennis game.

This company is also obligated in providing Community or Social Responsibility to the areas surrounding its developments by providing clean and safe environment, water resources, agricultural support to villagers and physical education through sports to both children and adults.

What the company does

HYDRO-POWER DEVELOPER (ENERGY SECTOR)
The main activities of NINETY TWO LIMITED in this sector is,

  1. Identification and ownership of viable hydro-power sites.
  2. To conduct implementation procedures.
  3. Construction of the power plant and infrastructures.
  4. Power Generation.
    The generated electricity in each Hydro-power plant is sold to Tanzania Electricity Supply Company (TANESCO).

Pinyinyi Small Hydro Power Project

Pinyinyi Small Hydro Power Project is a proposed run of-the-river development on the left bank of Pinyinyi River in Ngorongoro District, near Lake Natron (Soda Lake) within the United Republic of Tanzania. The proposed total installed capacity for the Project is 1.90 MW, comprised of two hydro turbine generator sets ...

Executive Summary

Pinyinyi Small Hydro Power Project (hereafter referred to as "the Project") is a proposed run-of-the-river development on the left bank of Pinyinyi River in Ngorongoro District, near Lake Natron (Soda Lake) within the United Republic of Tanzania. The proposed total installed capacity for the Project is 1.90 MW, comprised of two hydro turbine generator sets of 0.95MW each. The gross head available for power generation is ~236m, and the proposed design discharge is ~1.05 cumecs. The electricity generated is to be delivered to an isolated grid network system of Loliondo and Wasso via a planned 78km long 33KV transmission line. The proposed site is located on the Pinyinyi River around 7 km west of the shoreline of Lake Natron, close to the village of Pinyinyi. The location is approximately 57 km to the south-east of Loliondo Township. The site is around 150 km from Mta wa Mbu town towards the North. Pinyinyi Power Project is sponsored and owned by Ninety Two Ltd, a registered company in Tanzania, with offices at: Ninety-Two, Shekilango Road, Plot number 9, Block F UBUNGO, PO Box 79983, Dar-es-Salaam, Tanzania. Strategic Consulting Group (SCG), a hydro power consulting firm from India has been hired as technical consultant for the project. Tanzania has an estimated hydro power potential of around 4,700MW but only 561 MW of it has been developed so far. In the recent years, the Ngorongoro region has seen increasing demand for electricity due to the development in economic activity such as tourism, as well as population growth. Given the low access to electricity, heavy dependence on fossil fuels, low installed capacity and potential available, the Pinyinyi SHP is justified from all angles. The river Pinyinyi originates from Kenya and flows into Lake Natron in the Arusha region of northern Tanzania. The Pinyinyi River has a total catchment area of 1380 sq. km and 40% of the catchment is in Kenya. A significant portion of the catchment does not contribute to the run off. As per previous studies, the region is semi-arid and the rainfall is scanty. A long rain season from March to May & a short rain season in November-December are expected. Although the precipitation of the catchment is fairly distributed throughout the year substantial amount of it occurs during months of April & May. A team of Senior Engineers from the consultants visited the site and did a preliminary reconnaissance of the project site. The principal components of the project were identified and placed on the map. Subsequently, visits were conducted for carrying out detailed topographical surveys to freeze the layout of the site and establish the feasibility of the project. The Survey sheet for the project area is 27/4. From the available geological information for the site, the site is considered satisfactory for the construction of structures involved in a small hydro power project. The bearing capacity of all the proposed locations is adequate and no major problems are expected at this stage. Construction material such as aggregates, sand, boulders are available at locations near the site. The hydrology data for the river is limited and a long term series is not available. The sporadic information that is available from the gauging station at Oldonyo Sambu and from one near the Pinyinyi Village indicates that a dependable flow of 0.90 to 1.0 cumecs would be available at the river with 90% dependability. Based on this assumption, we have calculated the power generation potential of the project at around 13.78 GWh per year for 90% plant availability.

The major civil structures involved in the project are:

  1. A trench weir with shingle flushing conduit.
  2. An intake structure to collect water from the weir & direct it to the conveyance channel.
  3. A free flow conveyance channel to carry the water to the desilting tank.
  4. A desilting tank to separate all silt particles up to 0.20 mm size.
  5. A free flow water conductor system consisting of D Shaped head race tunnel (HRT) to carry the water to the forebay.
  6. A surface forebay (with storage of water equivalent to 2.5 minutes of operation) & penstock.
  7. A powerhouse at the base of the penstock to house the machines.
  8. Tail race Channel.

The design for civil structures was carried out in accordance with civil design principles & the estimated 100 year flood values. Since hydrology and flood flow information is limited, more studies are required to be conducted to estimate the 100 year return flood value. Two horizontal axis Pelton turbine, each of 0.95 MW capacity and two numbers of jets, have been proposed for the project. The turbine and generating units with other associated equipment will be accommodated in a surface powerhouse on the left bank of the river. The generation voltage is proposed to be 3.3 kV. This voltage will be stepped up to 33 kV level by two generator step-up transformers, rated (1.3 MVA), 3.3 kV/33 kV. On the LV side, the transformer will be connected to the generator by means of 3.3 kV isolated phase bus duct. On the HV side, the transformer will be connected to a 33 kV outdoor conventional type switchyard by a 33 kV overhead transmission line (link lines). Power will be evacuated through 33 kV Outdoor Switch Yard through single/double circuit 33 kV transmission line to the Loliondo grid station at a distance of 78 km. The main items of work for civil works have been estimated on the basis of drawings prepared after carrying out the designs of civil components. Surveys have been conducted to assess the availability and suitability of construction materials in the vicinity of the project area. The construction of Pinyinyi HEP will have to be supported by relevant infrastructure works such as permanent and temporary colonies, office, roads and bridges, workshops, etc. situated within the project area. The project is planned to be completed in a construction period of 18 months and a 6 - 7 month period will be devoted for creation of infrastructure facilities such as roads, housing, shelters, storage areas etc. The construction of the project is proposed to be carried out through contracting agencies entrusted with suitable contract packages. Suitable work force will be hired by the developer to execute the project in a judicious manner. The Environmental & Social Impacts Assessment (if required for this project) will be carried out in accordance with the terms of reference granted by the appropriate authority. This is a run-of-river type small hydro power project and is an environment friendly activity without any adverse impacts on the ecology of the area. In order to arrive at an estimate for the Project Cost, the major activities involved in the construction of the project have been identified and rates determined for the same. Also, the market rates & working rates for the major commodities involved in the construction of the project have been calculated. Based on these estimates, an estimate for the project cost is arrived at. Various activities involved during development of the project, cost of land, & other items are factored in. A financial model is built to calculate the financing cost, working capital requirement etc. After adding all these costs, the total project cost is calculated to be around USD 13.89 Million or USD 7.31 Million per MW of capacity installed. This includes the 78 km long transmission line and therefore is within the accepted range of costs for such projects. The tariff for the project as per the EWURA REFIT 2015 policy is 11.58 c/kWh, while the levelized cost of electricity generated is around 15.26 c/kWh. Since the project involves a large transmission and distribution component, the tariff required for economic viability of the project is higher. Thus, the project will be viable if a higher tariff is made available or a capital subsidy is provided by the government for the construction of the project. The financial projections are found to be encouraging. Sensitivity analysis is carried out for the project, varying the assumptions for critical variables such as project cost, hydrology, operational costs, etc. The sensitivity analysis indicates that the project has sufficiently robust cash flows to absorb variation in these inputs. Thus, the project is found to be technically feasible and economically viable (with subsidy). In conclusion, the Pinyinyi SHP is an economically & technically viable project and should be taken up for development & construction, provided that a capital subsidy is made available.


Nzowve Small Hydro Power Project

Nzowve Small Hydro Power Project is a proposed storage reservoir development on the left bank of Nzowve River in Sumbawanga District, near Lake Rukwa within the United Republic of Tanzania. The proposed total installed capacity for the Project is 8.0 MW, comprised of two pelton turbine generator sets of 4 MW each ...

Executive Summary

NZOWVE Small Hydro Power Project (hereafter referred to as "the Project") is a proposed storage reservoir development on the left bank of Nzowve River in Sumbawanga District, near Lake RUKWA within the United Republic of Tanzania. The proposed total installed capacity for the Project is 8.0 MW, comprised of two pelton turbine generator sets of 4 MW each. The gross head available for power generation is ~1100m, and the proposed design discharge is ~0.45 cumecs. The electricity generated is to be delivered to an isolated grid network system of Sumbawanga and Nkasi districts via a planned 38km long 66 KV transmission line. The proposed site is located on the Nzowve River in Mawenzuzi Village in Sumbawanga District, Rukwa region approximately 25 km south-east of Sumbawanga town . Nzowve Power Project will be sponsored and owned by Ninety Two Ltd, a registered company in Tanzania, with offices at: Ninety-Two, Shekilango Road, Plot number 9, Block F UBUNGO, PO Box 79983, Dar-es-Salaam, Tanzania. Strategic Consulting Group (SCG), a hydro power consulting firm from India has been hired as technical consultant for the project. Tanzania has an estimated hydro power potential of around 4,700MW but only 561 MW of it has been developed so far. In the recent years, the Sumbawanga region has seen increasing demand for electricity due to the development in economic activity such as tourism, agriculture, wood processing, Namwele coal, as well as population growth. Given the low access to electricity, heavy dependence on fossil fuels, low installed capacity and potential available, the Nzowve SHP is justified from all angles. As per previous studies, at the site in July 2009 the flows was between 0.2 and 0.3 cubic metres per second, measured flow by REA in late September 2009 was 0.27 cubic metres per second. This indicates more available water than previously estimated unless the area has been exposed to good rain in this period. The Nzowve River has a total catchment area of 82 sq. km at the proposed intake site.

A team of Senior Engineers from the consultants company will visit the site and do a preliminary reconnaissance of the project site. The principal components of the project will be identified and placed on the map. Subsequently, visits will be conducted for carrying out detailed topographical surveys to freeze the layout of the site and establish the detailed feasibility study of the project.

The major civil structures involved in the project are:

  1. A diversion weir at elevation EL + 1910m.
  2. An intake structure to collect water from the weir & direct it to the conveyance channel.
  3. A storage reservoir with approximately 1.4 Million metre cubic of storage.
  4. A free flow conveyance channel to carry the water to the desilting tank.
  5. A desilting tank to separate all silt particles up to 0.20 mm size.
  6. A surface forebay (with storage of water equivalent to 2.5 minutes of operation) & penstock of 4,400m long supported on piers and anchor blocks.
  7. A powerhouse with two pelton turbines of 4 MW each design flow 2*0.45 m3/s) at El. +815 m approximately, to be equipped with butterfly valves as closure arrangements
  8. Switch yard
  9. Tail race channel

The design for civil structures will be carried out in accordance with civil design principles & the estimated 100 year flood values. Since hydrology and flood flow information is limited, more studies are required to be conducted to estimate the 100 year return flood value. Two horizontal axis Pelton turbine, each of 4 MW capacity and two numbers of jets, have been proposed for the project. The turbine and generating units with other associated equipment will be accommodated in a surface powerhouse on the left bank of the river. The turbine and generating units with other associated equipment will be accommodated in a surface powerhouse on the left bank of the river. The generation voltage is proposed to be 6.6 kV. This voltage will be stepped up to 66 kV level by two generator step-up transformers, rated (5 MVA), 6.6 kV/66 kV. On the LV side, the transformer will be connected to the generator by means of 6.6 kV isolated phase bus duct. On the HV side, the transformer will be connected to a 66 kV outdoor conventional type switchyard by a 66 kV overhead transmission line (link lines). Power will be evacuated through 66 kV Outdoor Switch Yard through single/double circuit 66 kV transmission line to the Sumbawanga grid station at a distance of 38 km.

The main items of work for civil works will be estimated on the basis of drawings prepared after carrying out the designs of civil components. Surveys will be conducted to assess the availability and suitability of construction materials in the vicinity of the project area. The construction of Nzowve HEP will have to be supported by relevant infrastructure works such as permanent and temporary colonies, office, roads and bridges, workshops, etc. situated within the project area. The project is planned to be completed in a construction period of 18 months and a 6 - 7 month period will be devoted for creation of infrastructure facilities such as roads, housing, shelters, storage areas etc. The construction of the project is proposed to be carried out through contracting agencies entrusted with suitable contract packages. Suitable work force will be hired by the developer to execute the project in a judicious manner. The Environmental & Social Impacts Assessment required for this project will be carried out in accordance with the terms of reference granted by the appropriate authority. This is a storage reservoir type small hydro power project and is an environment friendly activity without any adverse impacts on the ecology of the area.


See also the project of sister company- Africa Power Investment:

Kikuletwa II Small Hydro Power Project
Proposed Installed Capacity - 8.00 MW

Kikuletwa River, Kilimanjaro Region, Tanzania

Executive Summary

Kikuletwa II Small Hydro Power Project (hereafter referred to as "the Project") is a proposed run-of-the-river development on the left bank of Kikuletwa River in Hai District, Kilimanjaro region within the United Republic of Tanzania. The proposed total installed capacity for the Project is 8.0MW, comprised of two hydro turbine generator sets of 4.0MW each. The gross head available for power generation is ~75m, and the proposed design discharge is ~14.5 cumecs. The electricity generated is to be delivered to the National Grid (Tanzania Electric Supply Co Ltd; TANESCO) via a 14 km long 66KV transmission line to the Kiyungi substation.

The Kikuletwa II project site is located around 22 km from Moshi town in the south-westdirection. The site is around 32km from the Kilimanjaro International Airport. Kikuletwa II Power Project is sponsored and owned by Africa Power Investment Ltd (API Ltd), a registered company in Tanzania, with offices at: Ninety-Two, Shekilango Road, Plot number 9, Block F UBUNGO, PO Box 79983, Dar-es-Salaam, Tanzania. Strategic Consulting Group (SCG), a hydro power consulting firm from India has been hired as technical consultants for the project. Tanzania has an estimated hydro power potential of around 4,700MW but only 561 MW of it has been developed so far. In the recent years, the Kilimanjaro region which comprises Moshi, Hai, Arusha, Rombo, Mwanga & Same areas has seen rapid development in economic activity as well as population growth. Given the low access to electricity, heavy dependence on fossil fuels, low installed capacity and potential available, the Kikuletwa II SHP is justified from all angles.

The river Kikuletwa originates in the south-western slopes of Mount Meru and Mount Kilimanjaro. The rivers Himo, Karanga, Weru Weru & Kware are the main tributaries of the River Kikuletwa. The river flows into the man-made reservoir called Nyumba Ya Munga and then merges into River Pangani. The Kikuletwa River has a total catchment area of 2,280 sq.km at the Kikuletwa II Power Station intake (including the catchment of its tributaries). The region generally has two rainy seasons. A long rain season from March to May & a short rain season in November-December. Although the precipitation of the catchment is fairly distributed throughout the year substantial amount of it occurs during months of April & May.

A team of Senior Engineers from the consultants visited the site and did a preliminary reconnaissance of the project site. The principal components of the project were identified and placed on the map. Subsequently, visits were conducted for carrying out detailed topographical surveys to freeze the layout of the site and establish the feasibility of the project. The Survey sheets for the project area are 56/3, titled Sanya Chini & 56/4, titled Moshi.

From the available geological information for the site, the site is considered satisfactory for the construction of structures involved in a small hydro power project. The bearing capacity of all the proposed locations is adequate and no major problems are expected at this stage. Construction material such as aggregates, sand, boulders are available at locations near the site. The daily discharge for the Kikuletwa River for the years 1971 – 2013, was obtained from the Gauging and discharge station maintained by the Ministry of Water at the Kikuletwa I power station (1DD54). The obtained data was subjected to rearrangement and statistical analysis. Based on the statistical analysis, the year 2004 was identified as the 75% dependable year in the data of 43 years. Based on incremental analysis for capacity, an 8.0 MW installed capacity was finalized as most economical and beneficial for the project.

The major civil structures involved in the project are:

  1. A gated non-overflow weir with under-sluice gates on the river bed
  2. An intake structure to collect water from the weir & direct it to the water conductor
  3. A free flow water conductor system consisting of part channel & part tunnel to carry the water to the forebay
  4. A surface forebay (with storage of water equivalent to 3 minutes of operation) & penstock
  5. A powerhouse at the base of the penstock to house the machines
  6. Tail race pool & Channels.

The design for civil structures was carried out in accordance with civil design principles & the estimated 100 year flood value of 200 cumecs. Two horizontal axis Francis turbine-generator units of 4.0 MW each have been proposed for the project. The turbine and generating units with other associated equipment will be accommodated in a surface powerhouse on the left bank of the river. The generation voltage is proposed to be 6.6 kV. This voltage will be stepped up to 66 kV level by two generator step-up transformers, rated (5 MVA), 6.6 kV/66 kV. On the LV side, the transformer will be connected to the generator by means of 6.6 kV isolated phase bus duct. On the HV side, the transformer will be connected to a 66 kV outdoor conventional type switchyard by a 66 kV overhead transmission line (link lines). Power will be evacuated through 66 kV Outdoor Switch Yard through single/double circuit 66 kV transmission line to the Kiyungi Substation of TANESCO at a distance of 14 km. The main items of work for civil works have been estimated on the basis of drawings prepared after carrying out the designs of civil components. Surveys have been conducted to assess the availability and suitability of construction materials in the vicinity of the project area.

The construction of Kikuletwa II HEP will have to be supported by relevant infrastructure works such as permanent and temporary colonies, office, roads and bridges, workshops, etc. situated within the projected area. The project is planned to be completed in a construction period of 18 months and a 6 - 7 month period will be devoted for creation of infrastructure facilities such as roads, housing, shelters, storage areas etc. The construction of the project is proposed to be carried out through contracting agencies entrusted with suitable contract packages. Suitable work force will be hired by the developer to execute the project in a judicious manner.

The Environmental & Social Impacts Assessment (if required for this project) will be carried out in accordance with the terms of reference granted by the appropriate authority. This is a run-of-river type small hydro power project and is an environment friendly activity without any adverse impacts on the ecology of the area.

In order to arrive at an estimate for the Project Cost, the major activities involved in theconstruction of the project have been identified and rates determined for the same. Also, themarket rates & working rates for the major commodities involved in the construction of the project have been calculated.

Based on these estimates, an estimate for the project cost is arrived at. Various activities involved during development of the project, cost of land, & other items are factored in. A financial model is built to calculate the financing cost, working capital requirement etc. After adding all these costs, the total project cost is calculated to be around USD 16.77 Million or USD 2.10 Million per MW of capacity installed.